Development Finance Costs 2026

Every cost on a development facility, line by line, and a worked example that adds them up

Development finance costs come in seven lines: the interest, which rolls up over the term; the lender’s arrangement fee; an exit fee, which some lenders charge and some do not; the valuation; the monitoring surveyor, who checks the build before each drawdown; the legal work on both sides; and the broker’s fee. On a typical scheme the interest is the largest of these and the fees together add a few percent of the loan on top. Our development finance page explains the product; this page is about what it costs.

The cost lines, one by one

Interest is charged monthly on what has been drawn and, on most facilities, rolled up rather than paid, so it is settled from the sale or refinance at the end. What sets the rate is on our development finance rates page.

The arrangement fee is the lender’s charge for setting the facility up, worked as a percentage of the loan and usually added to it rather than paid in cash. Because it is added, it attracts interest too.

An exit fee is charged by some lenders when the loan is repaid. It is worked either on the loan or on the GDV, and the difference matters: on a scheme worth twice what you borrowed, a fee on GDV is twice the size. Other lenders charge no exit fee and price the rate to suit, so we compare the two on total cost.

The valuation is the lender’s valuer’s report on the site value now and the GDV when finished. It is paid up front, and the cost rises with the size of the scheme.

The monitoring surveyor is the lender’s eyes on site. There is an initial report on the build cost and programme, then a visit before each drawdown to confirm the work claimed has been done. You pay for the initial report and each visit. On larger schemes a quantity surveyor’s cost plan sits alongside it.

Legal fees are paid on both sides. Your own solicitor handles the purchase and the loan; the lender’s solicitor handles its security, and you pay that bill too.

Our fee is agreed with you before you commit to anything. We tell you what it is at the start, not the end.

The architect, planning consultant, building regulations, structural warranty and contingency belong to the scheme rather than the finance, but a lender will ask where that money is coming from too.

A worked example: converting an office into six flats

This is an example, not a client, and the rate and fees in it are illustrative. A developer buys a former office for £450,000 with planning to convert it into six flats. The works are priced at £600,000, the lender wants a £60,000 contingency in the facility, the term is fifteen months and the GDV is £1,500,000. The lender funds 60% of the purchase, £270,000, and 100% of the works. Interest is 0.9% a month, rolled up.

Cost line How it is worked out Amount
Interest on the purchase tranche £270,000 x 0.9% x 15 months £36,450
Interest on the works, drawn evenly over 12 months average balance £300,000 x 0.9% x 12 months £32,400
Interest on the works during 3 months of sales £600,000 x 0.9% x 3 months £16,200
Arrangement fee 2% of the £930,000 net facility £18,600
Exit fee 1% of the loan, where charged £9,300
Valuation fixed fee £3,000
Monitoring surveyor initial report £2,500 plus six visits at £750 £7,000
Legal fees, both sides fixed fees £9,000
Total finance cost £131,950

The facility itself, with the contingency undrawn, comes to the £870,000 released plus £85,050 of interest and the £18,600 fee, so a little over £973,000 owed at the end, plus the exit fee where one is charged, against £1,500,000 of finished flats. The finance has cost about 8.8% of the end value. The developer put in £180,000 towards the purchase plus the third-party costs, the stamp duty and our fee, and if the six flats sell at £250,000 each the scheme returns around £318,000 before stamp duty on the purchase, our fee, selling costs and tax. Sizing the facility on your own figures is on our development finance calculator page.

The costs that catch people out

A late scheme is the expensive one. Every extra month adds interest on the full balance, and a lender will charge an extension fee to run past the agreed term, so a build that overruns by three months on the example above adds around £26,000 of interest before the extension fee. Refinancing a finished or nearly finished scheme onto development exit finance at a lower rate is often the answer, because it gives time to sell without the development rate running.

Undrawn money can cost too. Some lenders charge a non-utilisation fee on build money that sits unreleased, and some have a minimum interest period, so repaying at month four on a twelve-month facility does not save what you might expect. We check both before you sign. If your scheme will finish in a few months, a refurbishment bridge usually carries fewer of these lines and we will say so.

Questions people ask about development finance costs

How much does development finance cost in total?

In the example above, the interest and fees together come to just under 9% of the GDV over fifteen months. A real scheme can sit either side of that: shorter terms, less borrowing against the end value and a lender with no exit fee all bring it down.

Do I pay the fees up front?

The valuation, the monitoring surveyor’s initial report and the legal fees are paid as they arise, before and during the loan. The arrangement fee and the interest are usually added to the facility and paid from the sale or refinance at the end.

Is the interest charged on the whole facility from day one?

No. Interest runs on what has been drawn. The purchase tranche costs you from completion; each build drawdown costs you from the day the monitoring surveyor signs it off, so a build that finishes early saves interest.

Not all forms of Buy to Let, Commercial or Bridging loans are regulated by the Financial Conduct Authority.

Get the full cost of your facility before you commit

Send us the purchase price, the build cost, the term you expect and the sale values, and we will come back with the finance cost line by line, including our fee. Andrew has been in finance since 1989, and we would rather you saw the whole stack now than found an exit fee in the offer. The first conversation is free, by phone or through our contact page.